Object
Solihull Local Plan (Draft Submission) 2020
Representation ID: 10644
Received: 09/11/2020
Respondent: Hampton-in-Arden Parish Council and Catherine-de-Barnes Residents' Association
Number of people: 153
Legally compliant? Not specified
Sound? No
Duty to co-operate? Not specified
Para 224 indicates that that some of the larger sites will not make a significant contribution to completions until mid-delivery phase. There is no evidence to support this statement. All but one of the larger sites (BC1), consisting of over 300 dwellings, are to start in the 1st Phase and due to be delivered during periods I and II; there is no evidence of the scheduling of delivery through this period. 83% of the larger sites are due to commence delivery in period 1 and completion in
phase 2. No discussions have been held
to discuss the phasing of development.
See attachment