Q23. Are there any other comments you wish to make on the Draft Local Plan?

Showing comments and forms 31 to 60 of 389

No

Draft Local Plan Review

Representation ID: 602

Received: 30/01/2017

Respondent: Catherine Langton

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 623

Received: 31/01/2017

Respondent: Helen Young

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

200 houses on Site 3 between the Kenilworth Road and Windmill Lane
I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".
2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.
3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.
4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.
5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".
6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties
7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.
8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.
9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.
10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport
2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots
3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development
5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged
6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 631

Received: 01/02/2017

Respondent: Andy Wilson

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".
Having used the train service from Berkswell to Birmingham New Street for 7 years whilst at school, I was affected by the decision to cut the number of services down from 3 to 2 per hour. This was definitely not a frequent service as the decision led to me often getting home 40 minutes later as the Berkswell trains ran at 13 minutes past the hour and 53 minutes past the hour (my school day ended at 4 so I rarely was able to catch the 4:13). I sometimes instead had to travel to Hampton in Arden which was highly inconvenient.

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 656

Received: 02/02/2017

Respondent: Mr D Perks

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

Objection to the development site 3 @ windmill Lane
I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 664

Received: 01/02/2017

Respondent: Matthew Becker

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 728

Received: 05/02/2017

Respondent: Mr Roger Cook

Representation Summary:

Do not sacrifice the character of Knowle village in order to meets the needs of vested interests, developers, landowners and the Council who appear to be seeking to secure development through the easiest options available i.e. taking large tracts of land in Green Belt without seriously considering other options and alternatives

Full text:

In respect of the Draft Local Plan I am specifically concerned with the proposed development of Area 9 - South of Knowle for housing and the construction of a new Arden School campus as a result of funds being provided by the developers and land contributed by the local landowner (on condition housing is provided). The construction of 750 homes in this location is entirely inappropriate and the character of the village of Knowle will be destroyed. The infrastructure is inadequate, already stretched and will be unable to cope with such an increase in housing.

It also reflects poorly on the Council that strong rumours circulating in the local community as well as reflected by representatives in the Planning Department is that this is a 'done deal' because it serves the aims of developers, local landowners, Executive Principal of Arden School and other vested interests but it does not serve the character and community of Knowle.

By all means build a new school but do not fund it by selling out to the developers. Be creative and think of other funding means instead of ruining the village with unnecessary housing development.

No

Draft Local Plan Review

Representation ID: 781

Received: 05/02/2017

Respondent: Jean Fleming

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:


"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) I do not believe the central village has the parking, facilities or general capacity to deal with further growth within Balsall Common.

2) There are insufficient bus services to service the area resulting in more vehicle traffic and the resulting issues this causes.

3) The current crossing at the Kenilworth Road/Alder Lane/Kelsey Lane junction is already treacherous due to the many large lorries passing through, general volume of traffic and no pelican crossing. This is a nightmare for local children trying to get to school.

4) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the"very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.


5) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".


6) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.


7) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.


8) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

9) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties


10) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.


11) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.


12) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.


13) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:


1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development


5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 794

Received: 06/02/2017

Respondent: Amanda Miller

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:
"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"
I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.
The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.
1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".
2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.
3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.
4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.
5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".
6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties
7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.
9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.
10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."
In light of the above, I would support the recommendations from BARRAGE that:
1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport
2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots
3) The phasing of any development must recognise the impact and disruption of HS2
4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development
5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged
6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 798

Received: 06/02/2017

Respondent: David Miller

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:
"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"
I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.
The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.
1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".
2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.
3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.
4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.
5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".
6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties
7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.
9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.
10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."
In light of the above, I would support the recommendations from BARRAGE that:
1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport
2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots
3) The phasing of any development must recognise the impact and disruption of HS2
4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development
5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged
6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 814

Received: 06/02/2017

Respondent: Andrea Baker

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties. Although the primary school is currently within walking distance, the email sent by Mr Graeme Burgess, Head teacher of the primary school Academy last week clearly indicates that the school will be moving to a purpose built site in the short term, and therefore this will add additional traffic difficulties during what is already a heavily congested period.

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 819

Received: 17/12/2016

Respondent: Father Peter Thomas

Representation Summary:

Jaguar/Land Rover site will employ up to 3000 people. This has no mention in the local plan and will generate a minimum of 1000 vehicle movements twice a day using an already overloaded road network through Balsall Common. This is before adding the potential of 300 vehicle movements twice a day from the Frog Lane development alone. Majority of traffic movements to employment from the surrounding area are northwards. Further housing on the south side of Balsall Common will increase the traffic flows where roads are already identified as being congested. Need to consider effect of HS2 construction and traffic.

Full text:

I write after attending the Balsall Parish Council meeting last week. At that meeting many pieces of information were given by local residents regarding issues around the proposed local development plan and particularly the site at Frog Lane.

First we discover that it is proposed, at the Frog Lane site, to take the whole of the area, including the playing fields and allotments, out of the green belt with the suggestion that Frog Lane is a defensible boundary. I was told at the exhibition last August that the playing fields and allotments were not included and was assured, when I asked, that Frog Lane would not be widened/upgraded. In the plan now proposed it states the possible widening/upgrade of Frog Lane and has the playing fields and allotments included in the hatched area. The playing fields are a well used amenity for sports by the schools, other clubs and the general public. There are also many dog walkers making use of the fields. The Church has also used the fields for its youth groups as do the local brownies and guides. Both Chruch and brownie/guides meet regularly in premises next to the fields. Whilst we were told that the fields were not going to be developed I suspect that once they come out of greenbelt there will be pressure to develop them as it would be easy pickings. I also think that it is no co-incident that the day the proposals were published I receive an offer to purchase my house which boarders onto the playing fields. I also strongly believe that a widened/upgraded Frog Lane is no more a defensible boundary than the existing greenbelt boundary. For these reasons alone I make strong objection to the proposal.

Second we learn that the Jaguar/Land Rover site at the end of Holly Lane/Beres Lane will employ up to 3000 people. This is something that has no mention in the proposed local plan. If we assume that even a third of those will come from north of the site then that will mean a minimum of 1000 vehicle movements twice a day using an already overloaded road network through Balsall Common viz. Holly Lane, Gypsy Lane, Balsall Street and Kennilworth Road. All of this is before adding the potential of 300 vehicle movements twice a day from the Frog Lane development alone. We learnt that there is evidence that a majority of traffic movements to employment from the surrounding area are northwards thus building further housing on the south side of Balsall Common will increase further the traffic flows through the village which has already been identified as having some of the busiest roads in the borough of Solihull.

Thirdly it was noted that national planning guidelines were being ignored by SMBC that is:- a. the preference to use brownfield sites where possible, b. place new housing close to amenities such as doctors surgeries, shops, frequent public transport. There are brownfield sites closer to the amenities mentioned to the north of Balsall Common that could be used but are not included in the proposals. I therefore find it difficult to justify using greenbelt land in preference to the brownfield sites.

The proposals as they stand make no condition on development that infrastructure should be improved it is only 'suggested'.
First, on my calculations if Balsall Common were to receive over 1000 new houses that would entail about 50 school pupils per school year. This would mean the necessity of at least another 2 form entry primary school. The current primary school is already 4 form entry and is located on the south of the village. The secondary school site (also on the south side of the village) would struggle to find space to expand to take the extra pupils.
Second, we already have an inadequate congested commercial centre in Balsall Common with restricted parking. To increase the population without putting in plans to improve the centre substantially appears to be a grave mistake.
Third, there is no assurance that public transport is to be improved eg more frequent services and more parking at the rail station.
Fourthly there is no condition that any improvement/benefits for the community to come from the developments will be in place before, or even concurrent with any construction

I would also like to question whether there has been any consideration of the effect of the HS2 construction will have on the whole area around Balsall Common. With this construction going on at the same time as the proposals in the plan it will mean the current residents living effectively in a building site for 15 years with all the construction noise and traffic that will go with it.

I urgently appeal for a careful reconsideration of the proposals put forward for Balsall Common. I understand that there is a need for more housing and that Balsall Common should take some of these, however given the history of expansion over the past 30 years (four large housing estates and numerous infill and back garden development) with little change to the infrastructure it must be considered that Balsall Common is at saturation point without major public infrastructure work.

Peter Thomas
(Vicar St Peter's Balsall Common)

No

Draft Local Plan Review

Representation ID: 825

Received: 06/02/2017

Respondent: Mrs Catherine Kent

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

Yes

Draft Local Plan Review

Representation ID: 849

Received: 07/02/2017

Respondent: Mr David Bird

Representation Summary:

Where green belt land is to be used then the existing mature native trees should remain along with mature hedgerows and where possible controlled waters such as ponds, streams etc should be left open acting as wildlife corridors and not diverted through underground drainage pipes, such actions will reduce the impact to the local wildlife.

Full text:

Where green belt land is to be used then the existing mature native trees should remain along with mature hedgerows and where possible controlled waters such as ponds, streams etc should be left open acting as wildlife corridors and not diverted through underground drainage pipes, such actions will reduce the impact to the local wildlife

No

Draft Local Plan Review

Representation ID: 850

Received: 06/02/2017

Respondent: Mrs A Wildsmith

Agent: John Cornwell

Representation Summary:

Appendix C 'Schedule of Allocated Sites' should be amended to include allocation of residential land at Site 20. Either:
- 6.4ha, 150 dwellings, Dunstan Farm (see letter for more detail).
OR:

- 33ha, 700 dwellings, Land north and east of JLR Logistics and Operations Centre (see letter for more detail).

Full text:

see letter from agent on behalf of landowner

No

Draft Local Plan Review

Representation ID: 855

Received: 07/02/2017

Respondent: Mrs Gillian Dale

Representation Summary:

The White Paper on Housing being released tomorrow categorically states Green Belt should only be built on in exceptional circumstances. Where is the honest evidence for this in the Development Plan for Balsall Common? Why are brown field sites not being built on? When can i expect a response to my query?
Why make leaving comments so complicated? I believe its to put people off.
GIllian Dale

Full text:

Dear sir/madam,

I am writing to express my views on the proposed development in Balsall Common ( BC)I understand the need for more housing, I work with homeless teenagers. I also understand that when large developments are being proposed the infrastructure of the area needs to be considered, schools, access, health,etc. I am aware the potential building sites across Solihull have been weighted.

I am therefore confused as to why SMBC have chosen Frog Lane for development in BC given its lower scoring in relation to other sites around the borough.

Is there any awareness in SMBC as to the traffic congestion twice daily around the Balsall Street East, Holly Lane, Alder Lane and Gypsy Lane junction? This junction is an accident hotspot and has been for the last 19 years. I have witnessed and helped casualties from these accidents on many occasions. I have voiced my concerns to SMBC in the past regarding this issue.

May I suggest SMBC visit this junction during school opening and closing times to witness the chaos. This area is a danger to the pedestrians and vehicle users at these times . Surely potential development sites need such matters to be considered. Please inform me of how this traffic/ accident hotspot is weighted in comparison with other sites?

Several potential sites (some partially brownfield) were identified to the north of the village, and they all scored more highly than Frog Lane in terms accessibility, so why were they excluded? As a matter of urgency, we ask you to consider them now.

Does the proposed development of Frog Lane still include the playing fields?

I am interested to hear where the children of primary school age will be accessing their schooling given that BC Primary School tends to run at full capacity most years ( I was a school governor in the past) following the proposed development in BC.


I look forward to your response.

No

Draft Local Plan Review

Representation ID: 869

Received: 07/02/2017

Respondent: Paul Deane

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

OBJECTION to site 3, Kenilworth Road/Windmill Lane, Balsall Common
I am responding to the Council's Draft Local Plan with specific reference to Q15:


"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common) together with suitable brown field sites such as Site 1 which reduces the impact on true Green Belt fields, as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".


2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.


3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are14 PDL (Previously Developed Land) sites available, would strongly suggest thatdue consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.


4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties


7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.


8) The existence of the Berkswell Windmill (Grade II* listed building), as well asGreat Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.


9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.


10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:


1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development


5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 871

Received: 07/02/2017

Respondent: Wythall Parish Council

Representation Summary:

Need to ensure cooperation with Bromsgrove District Council and Worcestershire County Council with regard to cross boundary impacts from proposed developments.

Full text:

see attached letter

Yes

Draft Local Plan Review

Representation ID: 899

Received: 07/02/2017

Respondent: Richard Evans

Representation Summary:

23-I refer to my previous comments about the purpose of greenbelt and attach a document which I think is self explanatory. (Green Belt and its purpose)

Full text:

RESPONSES 1-YES
2-YES
Spatial Strategy
3- The size of the proposed developments around rural villages appears out of proportion to the size of the villages themselves. This is particularly exemplified in Balsall Common. The proposed by pass that would create an area of land between it and the A452 that would eventually be filled in with future housing developments.
The alternative options would be to concentrate future housing developments closer to the local areas of employment-JLR, Airport, NEC, Motor Cycle Museum, Birmingham Business Park and Hams Hall. There are sites available around Bickenhill, the junctions of the M6 AMD M42,Melbecks Garden Centre and even perhaps the site that was proposed for the new National Football Stadium before the new Wembley got the nod.
There are also areas around Water Orton and Coleshill which could be considered Sustainable Economic Growth
4-YES
5-YES
6-YES
7-YES
8-See previous answer to 3 9-YES
10-See previous answer to 3 PROVIDING HOUSES FOR ALL 11-YES
12-The principle of 50% affordable housing is laudable but judging by past local developments around Balsall Common this is never realised. The current Elysian Gardens Development is a case in point. The proportion of larger 2-5 bedroom detached houses always seem to dominate these development I suspect so the land owners and developers and landowners can maximise their profits.
13-No opinion
14-NO-Why should we have to take on a proportion of Birminghams number of development in the HMA. If you travel by train in from Berkswell to New Street their are plenty of unused brown field sites to be seen, are these not an option as green belt is cheaper to develop.
15-NO-Refer to answer to question 3.The main reason for the size of the "Barratts Farm" development appears to be to get funding from the developers to fund the proposed bypass to relieve congestion on the A452.As mentioned before this will inevitably lead to further infill development. The infrastructure of the village barely copes as it is, parking in the "thriving village centre" is already positively dangerous. Cars reverse out from both sides of the roads and there are frequents bumps and pedestrians being knocked over, I suspect a future fatality is inevitable.
16-As identified the infrastructure within Balsall Common is small. There is a lack of capacity at the primary and secondary schools. They are already over subscribed and have lack of space to expand into. Re-siting them would take them out of their central position where most pupils can walk to. If that were to happen additional school runs would be inevitable adding to the traffic congestion.
It is identified in the report that parking at the train station is inadequate, Hallmeadow road has become the unofficial overspill(part of the proposed bypass)
Extra parking is proposed but where. The only land by the existing car park is not being considered for the housing development because of recurrent flooding. As detailed in the report the number of car to house ratio at 1.6 is the highest in the borough so compounding the problem. As a regular cyclist I can assure you that adding cycle lanes on already narrow roads will not work.
The village centre is quoted as "thriving" in your report, the only useful development recently has been the addition of the Costa store where local people can meet up over coffee and socialise.
An obvious opportunity that has been lost is the development of the disused office block and
parking area for housing by the Co-op. This would have been an obvious site for a public funded facility for recreation and social needs-i.e. citizens advice, meeting area for the elderly/vulnerable and planned activities for the teenagers. Instead as before it has gone to the more profitable housing option. The village centre as it is has nowhere to expand to, and if moved would completely change the individuality of Balsall Common.
The only existing facility within the village that could cope with an increased local population is the new health centre. With an increase in patient number there will follow increased funding and an ability to employ more doctors and associated staff. The village badly needs a public funded development as previously mentioned that could provide recreational and social facilities
for the whole age range. The existing youth club is barely used for lack of activities leaving the streets and the park for the kids to fill their free time.
If the proposed developments do go ahead-3 in Balsall Common far more thought needs to be put into the impact they will have on theses small rural communities. The whole purpose of developing the concept of greenbelt and the greenbelt acts was to stop the creepage of large towns/cities into rural areas so they can keep their own unique character and charm. Increased urbanisation of the countryside between the cites of Birmingham and Coventry flies in the face of this agreed and accepted philosophy
17-YES
IMPROVING ACCESSIBILITY AND ENCOURAGING SUSTAINABLE TRAVEL 18-YES
PROTECTING AND ENHANCING OUR ENVIRONMENT.
19-YES
PROMOTING QUALITY OF SPACE
20-YES
HEALTH AND SUPPORT OF LOCAL COMMUNITIES
21-YES AND NO-There is an historic under funding of health care between Birmingham and Solihull as reflected by our local CCGs overspend and the combined Birmingham CCGs underspend. Perhaps this issue needs to be addressed at a Governmental level but it grates somewhat when we are expected to provide additional housing sites to make up for Birmingham's shortfall.
DELIVERING AND MONITORING 22-YES
ANY OTHER COMMENTS
23-I refer to my previous comments about the purpose of greenbelt and attach a document which I think is self explanatory.

No

Draft Local Plan Review

Representation ID: 905

Received: 07/02/2017

Respondent: Mrs Lorraine Horlor

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 909

Received: 07/02/2017

Respondent: Richard Coles

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

Balsall Common Draft Local Plan
I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 913

Received: 08/02/2017

Respondent: Sally Anne Coles

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

Balsall Common Draft Local Plan
I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 925

Received: 09/02/2017

Respondent: Nick Larkin

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:
"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"
I wish to object to the development of site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.
The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.
1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".
2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.
3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.
4) The development of site 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.
5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably cause delays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".
6) Site 3 scores poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties
7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.
9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 3. Given that the area is larger than site 3, this site should be re-assessed by the Council with a view to allocation instead of site 3.
10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time as HS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."
In light of the above, I would support the recommendations from BARRAGE that:
1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport
2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots
3) The phasing of any development must recognise the impact and disruption of HS2
4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development
5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged
6) Site 3 is removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 969

Received: 10/02/2017

Respondent: Mr Richard Drake

Representation Summary:

Disappointing that the emphasis is on Greenbelt and PDL sites as well as a new settlement have been ignored/dismissed

Full text:

Disappointing that the emphasis is on Greenbelt and PDL sites as well as a new settlement have been ignored/dismissed

No

Draft Local Plan Review

Representation ID: 1015

Received: 11/02/2017

Respondent: Colin Davis

Representation Summary:

Solihull Council have lost residents trust on new development
the consultation is too difficult to complete

Full text:

the plan
recent development like Dickens heath with its parking problems and apartments have soured people to be negative about new builds . expensive retirement apartments are springing up in our leafy surburbs taking out older character homes the Parkgate saga taking parkland for a supermarket and a few houses and high density builds on green space in North Solihull have blighted trust that quality of living and preserving Urbs in Rure is Solihull Councils aim.

the process
this is an incredibility difficult consultation to complete and i doubt anyone has found it easy to use your portal , the questions cover too many options and the answers very long to type . they are not just yes or no . why not just a comment box
it also excludes households who dont have a computer or dont feel comfortable with such a formal way of responding, i doubt this is a smart phone friendly format

Yes

Draft Local Plan Review

Representation ID: 1067

Received: 12/02/2017

Respondent: Mr Callum Hall

Representation Summary:

In summary, it has not been made clear why existing infrastructure (dual carraigeways) and the major source of work and transport flows (HS2 stations, Birmingham and motorways etc) have not led to housing being proposed in areas where this access is ideal. Instead, growth for Balsall Common is proposed at the opposite side of the village, maximising the pressure on the village's traffic capacity. Access to bus routes should not be a restriction on housing developments as you can simply change the bus routes to suit.

Full text:

In summary, it has not been made clear why existing infrastructure (dual carraigeways) and the major source of work and transport flows (HS2 stations, Birmingham and motorways etc) have not led to housing being proposed in areas where this access is ideal. Instead, growth for Balsall Common is proposed at the opposite side of the village, maximising the pressure on the village's traffic capacity. Access to bus routes should not be a restriction on housing developments as you can simply change the bus routes to suit.

No

Draft Local Plan Review

Representation ID: 1148

Received: 16/02/2017

Respondent: Solihull Mind

Representation Summary:

We have attached 4 documents to support our submission; 1.Overview of the service and issues.
2. Photographs showing the changes to the site - from an overgrown and derelict field to the current infrastructure and growing, conservation, leisure and sports activities that now make up the service - which we have achieved over the past 20 years.
3.Change.org petition signatures and comments.
4. A brief overview of the type of views expressed in response to the petition by service users, family and friends, mental health professionals and local people.

We hope these will demonstrate the value of our current service.

Full text:

We have attached 4 documents to support our submission; 1.Overview of the service and issues.
2. Photographs showing the changes to the site - from an overgrown and derelict field to the current infrastructure and growing, conservation, leisure and sports activities that now make up the service - which we have achieved over the past 20 years.
3.Change.org petition signatures and comments.
4. A brief overview of the type of views expressed in response to the petition by service users, family and friends, mental health professionals and local people.

We hope these will demonstrate the value of our current service.

No

Draft Local Plan Review

Representation ID: 1247

Received: 17/02/2017

Respondent: Friends of the Earth (Cities for People)

Representation Summary:

Policy P9 has much to say about climate change BUT where is the monitoring and reporting on the performance the council within the last plan and what is the direction of travel for the borough? The plan supports the expansion of the airport BUT fails to recognise that the aviation sector is a contributor to climate change. How are those emissions factored into the monitoring and reporting within this plan for example. Why have no minimum standards been set to reduce greenhouse gas emissions as mentioned in the sustainability appraisal?

Full text:

Policy P9 has much to say about climate change BUT where is the monitoring and reporting on the performance the council within the last plan and what is the direction of travel for the borough? The plan supports the expansion of the airport BUT fails to recognise that the aviation sector is a contributor to climate change. How are those emissions factored into the monitoring and reporting within this plan for example. Why have no minimum standards been set to reduce greenhouse gas emissions as mentioned in the sustainability appraisal?

No

Draft Local Plan Review

Representation ID: 1274

Received: 08/02/2017

Respondent: Lorna O'Regan

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:


I am responding to the Council's Draft Local Plan with specific reference to Q15:


"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"


I wish to object to the development of site 2 (Frog Lane, Balsall Common) and site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.


The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.


1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.


3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of sites 2 and 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.


5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably causedelays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".


6) Sites 2 and 3 score poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties


7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.


8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.


9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 2 and 3. Given that the area is larger than site 2 and 3, this site should be re-assessed by the Council with a view to allocation instead of site 2 and 3.



10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time asHS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to bothinfrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to"manage the growth."


Further to the above


11) Loss of public open space by removing Holly Lane Playing fields from the greenbelt and adding it onto site 2 at Frog Lane. This public space is used by the whole community. Dog walkers, families with children, joggers, walkers and the Girl Guides and Brownies from The Scout Hut on Holly Lane, Local football teams and the nearby Holly Lane Nursery.


In light of the above, I would support the recommendations from BARRAGE that:


1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport


2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2


4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development


5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 2 and 3 are removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 1283

Received: 08/02/2017

Respondent: Mark O'Regan

Representation Summary:

The phasing of any development in Balsall Common must recognise the impact and disruption of HS2.

Full text:

I am responding to the Council's Draft Local Plan with specific reference to Q15:

"Do you believe we are planning to build homes in the right locations? If not why not, and which locations do you believe shouldn't be included? Are there any other locations that you think should be included?"

I wish to object to the development of site 2 (Frog Lane, Balsall Common) and site 3 (Kenilworth Road, Balsall Common) and would propose that serious consideration be given to the development of site 240 (Wootton Green Lane, Balsall Common), as an alternative.

The reasons for my objection are below, based on the outcome of the investigations undertaken by the BARRAGE action group and as such the evidence and supporting information can be found in their report.

1) Balsall Common fails to meet the Council's own specified criteria for high frequency public transport and therefore is not a settlement with good accessibility. As such, the allocation of circa 20% of new housing in the Borough to Balsall Common, is in breach of SMBC's policy that "all new development should be focused in the most accessible locations".

2) Moreover it is a settlement with limited employment opportunities and therefore most people have to commute to work by car. A significant expansion will add unnecessary pressure to the road network as well adding to the carbon footprint. There are no proposed Sprint Runs to mitigate for this.

3) The proposed allocation of 3 greenfield sites in Balsall Common, when there are 14 PDL (Previously Developed Land) sites available, would strongly suggest that due consideration has not been given to these sites. As such, the "very special circumstances" to justify inappropriate development in the greenbelt have NOT been demonstrated.

4) The development of sites 2 and 3, being in the south of Balsall Common, will add to the congestion hotspots on the A452 caused by northbound traffic heading to the main employment centres.

5) The development of site 3 (200 units), in addition to the two sites currently under construction on the Kenilworth Road (115 units), will inevitably causedelays to drivers trying to access the A452. As a consequence, the risk of accidents will increase as drivers attempt to exit these sites in a situation even more difficult than it is today. Windmill Lane will become even more of a "rat run".

6) Sites 2 and 3 score poorly in relation to all accessibility criteria, as defined by SMBC, apart from the Primary School. As such most journeys to the shops, medical centre and railway station will have to be by car, adding to the existing congestion and parking difficulties

7) To alter the boundaries surrounding the Crest Nicholson developments on the Kenilworth Road (sites 22 and 23), in order to develop site 3, would directly contravene National policy, as these boundaries were regarded as permanent.

8) The existence of the Berkswell Windmill (Grade II* listed building), as well as Great Crested Newts, a European protected species, has been overlooked in the Council's assessment. As the setting of this iconic landmark will be harmed, the proposal is in breach of National policy.

9) Using the same criteria as the Council to assess sites, part- PDL site 240 outperforms site 2 and 3. Given that the area is larger than site 2 and 3, this site should be re-assessed by the Council with a view to allocation instead of site 2 and 3.

10) The phasing of all 3 proposed allocations for development to take place in years 1 - 5, at the same time asHS2 and the site at Riddings Hill, will place intolerable strain on the settlement. There will be insufficient time to effectively plan for and deliver the necessary improvements to both infrastructure and facilities, which are already overstretched. In particular, the current Primary School provision is wholly inadequate. This directly contravenes SMBC's stated intent to "manage the growth."

Further to the above

11) Loss of public open space by removing Holly Lane Playing fields from the greenbelt and adding it onto site 2 at Frog Lane. This public space is used by the whole community. Dog walkers, families with children, joggers, walkers and the Girl Guides and Brownies from The Scout Hut on Holly Lane, Local football teams and the nearby Holly Lane Nursery.

In light of the above, I would support the recommendations from BARRAGE that:

1) A re-assessment is made of the appropriateness of significantly expanding Balsall Common, given its poor accessibility using public transport

2) If there is justification for significantly expanding Balsall Common, then an holistic view is taken as to where housing is best located, with due consideration to be given to the re-use of PDL sites in preference to "greenfield" as well as congestion hot spots

3) The phasing of any development must recognise the impact and disruption of HS2

4) The necessary infrastructure to support any significant expansion must be identified and planned for alongside any development

5) SMBC consults on ALL PDL SITES, which fall within or are adjacent to Balsall Common, with a view to potential allocation with immediate effect to ensure the community is fully engaged

6) Site 2 and 3 are removed from the Draft Local Plan as it is not compliant with both National and Borough planning policies and, as such, is not sustainable.

No

Draft Local Plan Review

Representation ID: 1335

Received: 16/12/2016

Respondent: Oakwood Planning Ltd

Representation Summary:

SHELAA assessment for Oakwood House, Lavender Hall Lane call for sites reference 36 includes two mistakes, and should be corrected. The summary of availability contradicts the positive assessment under the availability criteria, and should read 'Site performs well against availability criteria', and the summary of achievability indicates moderate marketability/viability, unlikely to come forward within 5 years, when an application has already been discussed with the Parish Council and is likely to be submitted within a few months.

Full text:

I have been looking through the 2016 SHELAA carried out by Peter Brett Associates. I submitted the land adjacent Oakwood House, Lavender Hall Lane (submission attached). I think Peter Brett Associates have made a mistake in their assessment. I have attached their assessment.

The availability criteria says : Held by developer / willing owner / public sector, vacant land and buildings or sites with pre-app discussions are taking place. Site identified through submission process - therefore assume willing owner.
This is correct.
However, Peter Brett have then gone on to summarise: 'Site faces significant availability constraints'. This is contradictory with every other summary made in the SHELAA report with the same availability criteria. I believe it should read: 'Site performs well against availability criteria'.

In terms of the achievability, I do not understand why Peter Brett have summarised 2: Moderate marketability and/ or viability (unlikely to come forward within first five years)
We have already discussed the application with the parish council in the last 6 months, and are looking to submit in the next few months. The site is in an excellent location for marketability and is likely to come forward in the next 5 years.

Please could you look into these matters and let me know your response. I would also appreciate the document being corrected.