Q16. Do you believe we have identified the infrastructure[35] required to support these developments? If not why not? Are there any additional facilities you believe are required, if so what are the

Representation ID: 5589

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

Insufficient attention to necessary infrastructure provision and enhancements within the Borough to facilitate the scale of development being planned for by the Council. This represents a deficiency in Plan and its evidence base.
There are many related and complementary transport strategy documents and plans that are relevant to the LPR in terms of infrastructure projects.
Given the scale of planned investment in major transport infrastructure improvements and other planned interventions, it is concerning that the Draft LPR and its evidence base gives limited attention to the subject of infrastructure investment or its benefits for releasing major growth within the Borough.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).

Yes

Draft Local Plan Review

Q18. Do you agree with the policies for improving accessibility and encouraging sustainable travel? If not why not, and what alternatives would you suggest?

Representation ID: 5590

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

Support the principles of Policy P7 and P8. However, in terms of the evidence base, there is concern that the sustainability of the Arden Cross location has not been appropriately assessed.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).

Yes

Draft Local Plan Review

Q19. Do you agree with the policies for protecting the environment? If not why not, and what alternatives would you suggest?

Representation ID: 5591

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

Support the principles of Policy P9 and state that the Arden Cross proposals will make a significant contribution to this policy. However, concerns over the expectation that new development and specifically the UKC Hub area should develop and contribute to the development of heat networks within the Borough. This statement appears to have been generated in the absence of any Local Plan evidence to confirm the viability of such networks. The Heat Network delivery Unit Report is not specific to Solihull. Policy P9 should be amended to include a viability element.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).

No

Draft Local Plan Review

Q20. Do you agree with the policies for quality of place? If not why not, and what alternatives would you suggest?

Representation ID: 5592

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

Support the aims of Policy P15.
Object to paragraph 343 of the Plan which conflicts with the Vision and Spatial Strategy. These should be revisited to ensure suitable recognition that there will be necessary alterations to existing Green Belt boundaries within the Borough on the basis of identified exceptional circumstances
Support paragraph 349 of the Plan.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).

No

Draft Local Plan Review

Q22. Do you agree with the Policy P21? If not why not, and what alternatives would you suggest?

Representation ID: 5593

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

Policy P21 does not comprehensively set out how infrastructure provision and developer contributions will be sought.
The Infrastructure Delivery Plan is a critical part of the necessary supporting evidence base for the LPR. It must therefore be robustly updated ahead of the Pre-Submission stage consultation. This could require an 'overhaul' of the Council's previous approach to producing their IDP given the scale of new infrastructure investment in the Borough that will be necessary to deliver the scale of planned growth.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).

No

Draft Local Plan Review

Q23. Are there any other comments you wish to make on the Draft Local Plan?

Representation ID: 5594

Received: 17/02/2017

Respondent: Arden Cross Consortium

Agent: Turley

Representation Summary:

The Employment Land Review and Strategic Housing Market Assessment suffer from the lack of any substantive assessment of the implications of supergrowth for the purpose of evidence to support the current LPR.
The Accessibility Mapping Report has not undertaken a correct assessment of Site 19. A reappraisal using available information is required.
Disagree with some of the Sustainability Appraisal scores. The sustainability benefits of Site 19 are not recognised. Comments on the sustainability appraisal should be reflected in the next iteration of the document.

Full text:

On behalf of our client, the Arden Cross Consortium, please find attached a copy of representations submitted to the public consultation on the Solihull Draft Local Plan Review (November 2016) and Interim Sustainability Appraisal Report (January 2017).