Solihull Local Plan (Draft Submission) 2020

Search representations

Results for Society for the Protection of Ancient Buildings search

New search New search

Object

Solihull Local Plan (Draft Submission) 2020

Policy BC3 - Kenilworth Road/Windmill Lane, Balsall Common

Representation ID: 13853

Received: 08/12/2020

Respondent: Society for the Protection of Ancient Buildings

Legally compliant? Not specified

Sound? No

Duty to co-operate? Not specified

Representation Summary:

Objection (Wants site BC3 removed from Solihull Draft Submission Local Plan and Final Local Plan): Fails 3/4 tests of soundness.
> Not positively prepared as it is not practical to deliver the unmet need of the HMA (2105 units). NPPF para. 11 has not been given due consideration. To build 4410 units (Greenfield) and 1195 units (Meridian Gap) is not required to comply with planning policy. Furthermore, site BC3 specifically is not sustainable using the council’s own criteria.
> Allocation of site BC3 has not been justified. Omission of sites within Balsall common and in the wider Borough which should have been chosen based on merit or for which the omission has not been justified. Final findings from Solihull Town Centre Masterplan are not incorporated and cannot be reconciled with the Draft Local Plan.
>Inconsistencies with the NPPF, specifically para 1; 94; 108; 109; 122; 138; 185 and 194 are not complied with. Sustainable development will not be complied with if site BC3 remains in the Draft Local Plan.
>Wishes to preserve the biodiverse rich habitat that is Site BC3 and protect the character of the Grade II Listed Berkswell Windmill.

Full text:

Objection to Site BC3- Fails 3 out 4 Tests of Soundness
I wish to formerly object to Site BC3 Windmill Lane/Kenilworth Road and ask that it is
removed from Solihull’s Draft Local Plan and Final Local Plan.
The Draft Local Plan is not sound, in proposing the allocation of Site BC3 for housing, as it
fails to comply with 3 of the 4 tests of Soundness:
1) Positively Prepared:
The plan has not been positively prepared in that it is not practical to deliver the
unmet need of the HMA (2105 units). NPPF para. 11 has not been given due
consideration. To build 4410 units on Green Belt Land (greenfield) and 1195 in the
Meriden Gap is not required in order to comply with planning policy. Moreover, it is
demonstrated that Site BC3 specifically is not sustainable using the Council’s own
criteria.
2) Justified:
The allocation of site BC3 has not been justified. There are omission sites both within
Balsall Common and in the wider borough which either should have been allocated,
based on merit, or for which the omission has not been justified. Moreover, the
findings from the final version of the masterplan for Solihull Town Centre have not
been included. This is due for publication by the year end.
3) Consistent with National Policy:
Inconsistencies with the NPPF are demonstrated throughout this report. Specifically
paragraphs 11; 94; 108; 109; 122; 138; 185 and 194 are not complied with. As such,
the enabling of sustainable development will not be delivered should Site BC3
remain in the Draft Local Plan.
I wish to protect the biodiverse rich habitat that is Site BC3 and I also wish to protect the
setting and character of the Grade II * Listed Berkswell Windmill.

Attachments:

Object

Solihull Local Plan (Draft Submission) 2020

Balsall Common

Representation ID: 14589

Received: 14/12/2020

Respondent: Society for the Protection of Ancient Buildings

Legally compliant? Not specified

Sound? No

Duty to co-operate? Not specified

Representation Summary:

Object to Site BC3.
It is not practical to deliver the unmet need of the HMA (2105 units). NPPF para. 11 has not been given due consideration. To build 4410 units on Green Belt Land (greenfield) and 1195 in the Meriden Gap is not required in order to comply with planning policy. Moreover, it is demonstrated that Site BC3 specifically is not sustainable using the Council’s own criteria.
There are omission sites both within Balsall Common and in the wider borough which either should have been allocated, based on merit, or for which the omission has not been justified. The findings from the final version of the Solihull Town Centre Masterplan are not incorporated.
There are inconsistencies with the NPPF, specifically paragraphs 11; 94; 108; 109; 122; 138; 185 and 194 are not complied with. As such, the enabling of sustainable development will not be delivered should Site BC3 remain in the Draft Local Plan. The biodiversity and setting and character of the Grade II * Listed Berkswell Windmill should be protected

Change suggested by respondent:

Site BC3 should be removed from the Plan

Full text:

Objection to Site BC3 - Fails 3 out 4 Tests of Soundness I wish to formally object to Site BC3 Windmill Lane/Kenilworth Road and ask that it is removed from the Solihull Draft Submission Local Plan and Final Local Plan. The Draft Submission Local Plan is not sound, in proposing the allocation of Site BC3 for housing, as it fails to comply with 3 of the 4 tests of Soundness: 1) Positively Prepared: The plan has not been positively prepared in that it is not practical to deliver the unmet need of the HMA (2105 units). NPPF para. 11 has not been given due consideration. To build 4410 units on Green Belt Land (greenfield) and 1195 in the Meriden Gap is not required in order to comply with planning policy. Moreover, it is demonstrated that Site BC3 specifically is not sustainable using the Council’s own criteria. 2) Justified: The allocation of site BC3 has not been justified. There are omission sites both within Balsall Common and in the wider borough which either should have been allocated, based on merit, or for which the omission has not been justified. Moreover, the findings from the final version of the masterplan for Solihull Town Centre are not incorporated and cannot be reconciled with the Draft Local Plan. 3) Consistent with National Policy: There are inconsistencies with the NPPF. Specifically paragraphs 11; 94; 108; 109; 122; 138; 185 and 194 are not complied with. As such, the enabling of sustainable development will not be delivered should Site BC3 remain in the Draft Local Plan. I wish to protect the biodiverse rich habitat that is Site BC3 and I also wish to protect the setting and character of the Grade II * Listed Berkswell Windmill.

Object

Solihull Local Plan (Draft Submission) 2020

Policy BC3 - Kenilworth Road/Windmill Lane, Balsall Common

Representation ID: 15158

Received: 08/12/2020

Respondent: Society for the Protection of Ancient Buildings

Legally compliant? Not specified

Sound? Not specified

Duty to co-operate? Not specified

Representation Summary:

Objection to Site BC3;
Any building between 200 and 250 degrees from Berkswell Mill will damage the sustainability and operation of the Windmill - Housing will reduce the amount available to the windmill and increase turbulence to which it will be subjected - reduced attraction to visitors/increase in maintenance costs

Full text:

See attachment

Attachments: